Procurement pipeline by work package

Procurement pipeline

Scope of works first
  1. Not started1
  2. Scope of works1
  3. Tender issued0
  4. Tenders received1
  5. Recommendation0
  6. Awarded1
  7. Contract executed5

The scope of works is written and approved first. Its items become the RFT schedule, the rows of the tender comparison matrix, the subcontract inclusions, and the baseline every later variation is measured against — one list, never retyped. A package cannot reach tender_issued while its scope is unapproved.

Tender comparison, subcontract records and compliance trackingdocs/17-contracts-and-procurement.md

Work packages

95 contracted
CodePackageOwnerStage
WP-02StructureMarcus ReyesContract executed
WP-06FaçadeMarcus ReyesContract executed
WP-11Hydraulic servicesSam OkaforContract executed
WP-12Mechanical servicesSam OkaforContract executed
WP-13Electrical servicesSam OkaforAwarded
WP-21TilingDana ChenContract executed
WP-20WaterproofingDana ChenTenders received
WP-24JoineryUnassignedScope of works
WP-26PaintingUnassignedNot started