Whole projectRiverside Tower
Stage 2Hutchinson24° · 0mm · Sydney
Contract value
$48.2M
Practical completion
14 Mar 2027
Scope
Whole project
Programme
62%
Day 284 of 520
My actions
13| Ref | Item | Due | |
|---|---|---|---|
| ITP-0142 | L3 slab pour — pre-pour — sign off | Today | |
| ITP-0151 | L3 shower bases — waterproofing — sign off | Overdue | |
| ITP-0144 | L3 in-wall services rough-in — sign off | Overdue | |
| ITP-0148 | L1 switchboard termination — sign off | Overdue | |
| ITP-0152 | Façade Zone A — sealant — sign off | Overdue | |
| VAR-018 | Façade panel change — Zone A — approval $84k | Overdue | |
| DIARY | Tuesday site diary not submitted | Overdue |
Daily brief
AI- 1
Four hold points are overdue across structure, services and façade.
- 2
Joinery and painting have no owner — nobody is chasing either trade.
- 3
Weather: the pour window closes Thursday.
Programme
| Activity | Status |
|---|---|
| L3 slab pour | On time |
| Façade Zone A | 4d late |
| Services rough-in | On time |
| Practical completion | 14/03/27 |
Cost
Head contract| Contract | $48.20M |
| Approved variations | $1.84M |
| Pending variations | $0.41M |
Unassigned packages
2 to assignAssign| Code | Package | Stage | |
|---|---|---|---|
| WP-24 | Joinery | Scope of works | |
| WP-26 | Painting | Not started |
Recent plans
4Open plansActivity
D. Chen issued H-301 Rev C — aligned on upload
12mArup issued 9 drawings to L3
1hM. Reyes signed ITP-0138
3hAce Tiling requested inspection on ITP-0155
4hS. Patel raised RFI-094 — slab penetration
5hSealtec submitted tender for waterproofing
1d